Road Closure: A528 Burlton to Tunnel Bank
Start Date: 2nd September 2024
End Date: 17th September 2024
Purpose: Multevo carriageway repairs to include kerbing, sign posts and iron works. Completion of 1300m2 required. Section 1: A528 Burlton to Cockshutt 02/09/2024-11/9/2024 (09:30-14:45) Section 2:- A528 Cockshutt to Colemere Woods 11/09/2024-16/09/2024 (09:30-14:45) Section 3:- Colemere Woods to Tunnel Bank 16/09/2024-17/09/2024 (09:30-16:00) Only one section will be in place at any one time.
Works Promoter: Multevo for Shropshire Council
Works Promoter Ref: UJ20822208325/UJ20842649530/UJ20839474393/UJ20866059233/UJ20814344196
Enforcement pattern for A528 Burlton to Tunnel Bank:
From Monday to Friday 09:30 – 16:00
You can view the closure and diversion route by clicking here: https://one.network/?tm=139107998
Should you have any queries regarding this closure, please call Customer Services on 0345 6789006, or contact the Street Works Team on streetworks@shropshire.gov.uk